Aktau, Kazakhstan
Caspi Bitum Plant
حول رقم الطاقة: Orda.kz reports an upgrade that lifted refining from 1.0 to 1.5 Mt per year (about 30,000 bpd) and bitumen from 500,000 to 750,000 t, with a restart on 5 May 2025. KMG annual report 2024 still shows 1.0 Mt design and 327 kt throughput, and says the upgrade targets 1.5 Mt and 700 kt of road bitumen.
ما ينتجه
البيتومين
عن هذه المصفاة
Caspi Bitum is a bitumen refinery at Aktau, a joint venture of KazMunayGas and CITIC. It started in December 2013 and was expanded to 1.5 million tonnes of oil a year and 750,000 tonnes of bitumen a year, with a relaunch reported in May 2025. It is described as the largest road bitumen producer in Central Asia.
تشكيلة الخامات: Karazhanbas field crude (Orda.kz).
إمكانية التصدير: Aimed at the domestic road market; no export routes stated.
على الخريطة
المحطات والموانئ القريبة
مصافٍ أخرى في Kazakhstan
- Planned fourth Kazakh refinery200,000 bpd
- Pavlodar Refinery (Pavlodar Petrochemical Plant)120,000 bpd
- Shymkent Refinery (PetroKazakhstan Oil Products)120,000 bpd
- Atyrau Refinery110,000 bpd
- Shymkent Refinery Expansion (12 Mt per year project)Not published
- Kazakhstan Petrochemical Industries gas chemical complexNot published
- Karachaganak Gas Processing PlantNot published
موقع المشغّلاطلب منتجات من هذه المنطقة
إدراج كيان هنا ليس تزكية، ولا يعني أنه يمكن التعامل معه قانونيا. كثير من الكيانات في إيران وروسيا وسوريا وفنزويلا ودول أخرى خاضع للعقوبات. افحص كل طرف قبل أي تواصل.
المصادر
- KMG Annual Report 2023, Downstream review
- Caspi Bitum plant restarts after modernization (Orda)
- KMG Annual Report 2024, downstream
كُتب بأسلوب PST من المصادر أعلاه. الثقة في البيانات: medium. أبلغ مكتب PST بأي تصحيح.