Complex or hub · Ras Lanuf, Libya

Ras Lanuf is Libya's main refining and petrochemical site on the Gulf of Sirte. The refinery and an ethylene and polyethylene complex are run by a subsidiary of the National Oil Corporation.

خوراک
Crude oil and associated gas
تولید می‌کند
Refined products, Ethylene, Polyethylene
بهره‌برداران
Ras Lanuf Oil and Gas Processing Company, National Oil Corporation

جریان فرایند

کارکرد

The Ras Lanuf refinery was completed in 1984 with a capacity of 220,000 barrels a day and is run by the Ras Lanuf Oil and Gas Processing Company, a subsidiary of the National Oil Corporation. The site's petrochemical complex includes an ethylene plant, a polyethylene plant, utilities and the Port of Ras Lanuf. The port is mainly used for loading crude oil and products and has a maximum draft of 22 metres. Pipelines from Amal, Messla and Defa fields reach Ras Lanuf. Capacities of the petrochemical plants are not stated, and the site has had interruptions in the past.

گام‌به‌گام

  1. Pipelines bring crude from fields
  2. Refinery processes crude
  3. Ethylene plant uses refinery and gas streams
  4. Polyethylene plant makes polymer
  5. Port loads crude and products

شیمی

Chain: ethylene to polyethylene.

تجهیزات اصلی

  • Refinery units
  • Ethylene plant
  • Polyethylene plant
  • Port loading terminal

ایمنی

Operations have been affected by conflict in the past, so check current status.

در خلیج فارس

The refinery was completed in 1984 at 220,000 bpd. The port has a maximum draft of 22 m. Libya is a North African feed and supply route for Gulf traders, but the status of the petrochemical plants should be checked before trading.

خودتان را بسنجید

پرسش 1 از 3 · امتیاز 0 · رکورد پیاپی 0

When was the Ras Lanuf refinery completed?

مرتبط

منابع

با بیان خود PST و بر پایهٔ منابع بالا نوشته شده است. اطمینان از داده: medium. واحدهای واقعی از نظر طراحی و شرایط بهره‌برداری تفاوت دارند.