Baku, Azerbaijan
Heydar Aliyev Baku Oil Refinery
Sobre o dado de capacidade: EIA 2023 gives 120,493 b/cd. OGJ says more than 6 Mt per year and about 6.3 Mt processed in 2023 (equal to about 126,000 bpd, so throughput slightly exceeds the EIA figure). Trend cites 6.5 Mt. Modernisation targets 7.5 Mt; the Euro 5 fuels complex started up in June 2024.
O que produz
Gasolina
Diesel and gasoil
Sobre esta refinaria
SOCAR's main refinery in Baku began as the New Baku Oil Refinery in 1953 and was merged with the neighbouring Azerneftyag plant from 2015. A modernisation programme started in 2015, with phase one finished in December 2018 including a bitumen unit raising bitumen output to 400,000 tonnes a year. The target is 7.5 million tonnes a year and Euro-5 fuels.
Cesta de petróleos: Processes 21 of 24 crude grades per Offshore Technology; mainly Azeri light and other Caspian crude
Acesso de exportação: Caspian coast at Baku; propane-propylene and butane-butylene fractions are piped to Azerikimya
No mapa
Terminais e portos próximos
- Heydar Aliyev Baku Oil Refinery0 km · Refinery tank farm
- Sangachal Terminal44 km · Export terminal
- Baku Oil Terminal (Azertrans)63 km · Port and anchorage
Outras refinarias em Azerbaijan
Site do operadorSolicitar produtos desta região
Constar aqui não é um aval e não significa que se possa negociar legalmente com a entidade. Muitas entidades no Irão, Rússia, Síria, Venezuela e outros países estão sujeitas a sanções. Faça a triagem de todas as partes antes de qualquer contacto.
Fontes
- Offshore Technology, Heydar Aliyev Oil Refinery
- OGJ, SOCAR commissions unit, wraps Phase 1
- EIA Caspian Sea regional analysis
- OGJ: Baku refinery starts up fuels plant
Redigido com as palavras da própria PST a partir das fontes acima. Confiabilidade dos dados: medium. Informe uma correção à mesa da PST.