Baku, Azerbaijan
Heydar Aliyev Baku Oil Refinery
О показателе мощности: EIA 2023 gives 120,493 b/cd. OGJ says more than 6 Mt per year and about 6.3 Mt processed in 2023 (equal to about 126,000 bpd, so throughput slightly exceeds the EIA figure). Trend cites 6.5 Mt. Modernisation targets 7.5 Mt; the Euro 5 fuels complex started up in June 2024.
Что производит
Бензин
Diesel and gasoil
Об этом НПЗ
SOCAR's main refinery in Baku began as the New Baku Oil Refinery in 1953 and was merged with the neighbouring Azerneftyag plant from 2015. A modernisation programme started in 2015, with phase one finished in December 2018 including a bitumen unit raising bitumen output to 400,000 tonnes a year. The target is 7.5 million tonnes a year and Euro-5 fuels.
Корзина сортов нефти: Processes 21 of 24 crude grades per Offshore Technology; mainly Azeri light and other Caspian crude
Доступ к экспорту: Caspian coast at Baku; propane-propylene and butane-butylene fractions are piped to Azerikimya
На карте
Ближайшие терминалы и порты
- Heydar Aliyev Baku Oil Refinery0 km · Refinery tank farm
- Sangachal Terminal44 km · Export terminal
- Baku Oil Terminal (Azertrans)63 km · Port and anchorage
Другие НПЗ в стране: Azerbaijan
Сайт оператораЗапросить продукты из этого региона
Включение организации в список не является одобрением и не означает, что с ней можно работать на законных основаниях. Многие организации в Иране, России, Сирии, Венесуэле и других странах находятся под санкциями. Проверяйте каждую сторону до любого контакта.
Источники
- Offshore Technology, Heydar Aliyev Oil Refinery
- OGJ, SOCAR commissions unit, wraps Phase 1
- EIA Caspian Sea regional analysis
- OGJ: Baku refinery starts up fuels plant
Написано собственными словами PST по источникам выше. Достоверность данных: medium. Сообщить об исправлении можно команде PST.