Khor Mor, near Chamchamal, Sulaymaniyah, Iraq
Khor Mor Gas Processing Plant
原油蒸馏能力未公布
开始时间2008
复杂度-
船东Pearl Petroleum (Dana Gas 35%, Crescent Petroleum 35%, OMV 10%, MOL 10%, RWE 10%)
关于产能数据: Gas plant: 750 million scf/d after the KM250 expansion completed October 2025, with condensate of 15,200 bpd plus 7,000 bpd added, and LPG of 1,070 t/d plus 460 t/d added.
产出
LPG
Condensate products
关于本炼厂
Largest gas processing plant in the Kurdistan Region, producing sales gas, LPG and condensate. The KM250 expansion finished in October 2025, eight months early.
原油配比: Khor Mor field gas
导出权限: Domestic supply, mainly to Kurdistan power plants
在地图上
30 在地图上
附近的码头和港口
- Kirkuk modern oil depot56 km · Storage terminal (commercial)
- Baiji refinery134 km · Refinery tank farm
Iraq 的其他炼厂
- Baiji Refinery (Salahuddin and Baiji North)310,000 bpd
- Fao Refinery300,000 bpd
- Basra Refinery (Shuaiba)260,000 bpd
- Nasiriyah (Dhi Qar) Refinery150,000 bpd
- Kirkuk New Refinery150,000 bpd
- Mirsan Refinery150,000 bpd
- Daura Refinery140,000 bpd
- Karbala Refinery140,000 bpd
此处列出的实体不代表背书,也不意味着可以合法与其交易。伊朗、俄罗斯、叙利亚、委内瑞拉和其他国家的许多实体受到制裁。在任何接触之前,请对每一方进行筛查。
来源
- Iraq Business News, Khor Mor Gas Expansion Completed Eight Months Early
- Crescent Petroleum, KM250 completion
由 PST 依据上述来源自行撰写。数据可信度:medium。如有更正,请告知 PST 交易台。